LUL - G1168
Premises: Reactive Maintenance Works (Second Line Response)
Organization: | LUL |
Publication Date: | 1 July 2015 |
Status: | active |
Page Count: | 8 |
scope:
This Guidance applies to all the Reactive Maintenance Works ensuring that the requirements of the following listed documentation and CED Standards are followed and met:
W0001.A2 Minor Works
G136.A2 Control of works on LU Premises
S1538 Assurance
Purpose
The purpose of this Guidance is to describe the process used within APD (Premises and structures area) to control the Reactive Maintenance Works, from initial request or identification of works through to sign off of completed works to ensure that there is a minimum delay and disruption to LUL's business