scope:
Includes: This document details the routine maintenance to be carried out on the Programmable Logic Controller (PLC) for the main D.C. Contactors at
Ludgate Cellars Substation (see figure 1).
Excludes: These instructions do not include the routine maintenance of either the main D.C. Contactors at Ludgate Cellars Substation or the Trackside
Slave Contactors (TSC) at Blackfriars station.
Document History
NR/L3/ELP/27240/NR/D/C34D
December 5, 2020
Routine Maintenance of the AC/DC Interface Programmable Logic Controller (PLC) at Ludgate Cellars Substation
Includes: This document details the routine maintenance to be carried out on the Programmable Logic Controller (PLC) for the main D.C. Contactors at
Ludgate Cellars Substation (see figure 1)....