NR/L3/TRK/1015/MOD03 ISSUE 1
Management of Basic Visual Inspection: Inspection for RBM Regimes
| Organization: | NR |
| Publication Date: | 5 March 2022 |
| Status: | active |
| Page Count: | 12 |
scope:
This module is for use by Section Managers [Track] (SM[T]) and applies to standardised RBM Inspection activities as set-out in NR/L2/TRK/7014 and bespoke themed track inspection activities derived using NR/L2/MTC/10662.
It does not apply to:
a) TME inspections; or
b) special inspections.
NOTE: For example those associated with hot weather, adverse weather, following an incident report or flooding).
Purpose
This module provides a process for the management of Themed Inspections for all Risk Based Maintenance (RBM) Regimes, known as 'RBM Inspections', to achieve a consistent approach across the network to;
a) improve the reliability and quality of RBM Inspections; and
b) develop the skill and competence of staff.
Document History