scope:
This document covers all testing as defined by the following detail:
System performance tests.
Short circuit tests.
Section proving on new systems and following system alterations.
Running of Mentor or equivalent measurement vehicle.
Running of the Load Bank.
Any other testing that requires the non-routine connection to or alteration of the Overhead Line or Conductor Rail System.
Purpose
This document sets out the requirements for carrying out testing of electrification systems and equipment.