scope:
Introduction
This is a joint inspection to be carried out with the track organisation.
The objective of this inspection is to identify parts that may require renewal or major adjustment. Careful inspection at this stage will mean that you will be fully equipped with both the tools and spares that are required on the day of the Pointcare service.
It should be noted that the Pre-inspection is only an inspection of the equipment (i.e. taking measurements and a general examination) and will not require possession of the points for more than a few minutes.
Document History