MODUK - DEF STAN 59-41: PT 3: SUPP S
Electromagnetic Compatibility Part 3: Technical Requirements Test Methods and Limits Supplement S: Test Method DCS11 Imported Long Transient Susceptibility - Power Lines (Sea Systems)
inactive, Most Current
| Organization: | MODUK |
| Publication Date: | 1 January 1996 |
| Status: | inactive |
| Page Count: | 10 |
scope:
Purpose
The purpose of this test is to ensure that transients typical of those produced by group switching of equipments on power lines will not damage or cause malfunction of the EUT.
Document History
DEF STAN 59-41: PT 3: SUPP S
January 1, 1996
Electromagnetic Compatibility Part 3: Technical Requirements Test Methods and Limits Supplement S: Test Method DCS11 Imported Long Transient Susceptibility - Power Lines (Sea Systems)
Purpose
The purpose of this test is to ensure that transients typical of those produced by group switching of equipments on power lines will not damage or cause malfunction of the EUT.