UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

NG SCT 08.01

Site Commissioning Tests - Interlocking

active, Most Current
Buy Now
Organization: NG
Publication Date: 1 November 2013
Status: active
Page Count: 5
scope:

PURPOSE AND SCOPE

This document contains the site commissioning checks and tests to be performed on the installation of electrical and mechanical interlocking in National Grid (NG) substations.

Document History

NG SCT 08.01
November 1, 2013
Site Commissioning Tests - Interlocking
PURPOSE AND SCOPE This document contains the site commissioning checks and tests to be performed on the installation of electrical and mechanical interlocking in National Grid (NG) substations.