scope:
PURPOSE AND SCOPE
This document contains the site commissioning checks and tests to be performed on the installation of electrical and mechanical interlocking in National Grid (NG) substations.
Document History
NG SCT 08.01
November 1, 2013
Site Commissioning Tests - Interlocking
PURPOSE AND SCOPE
This document contains the site commissioning checks and tests to be performed on the installation of electrical and mechanical interlocking in National Grid (NG) substations.