NR SSI8505D
SSI Data Procedures - Chapter D: Installation, Testing and Commissioning
| Organization: | NR |
| Publication Date: | 5 September 2015 |
| Status: | active |
| Page Count: | 23 |
scope:
Introduction
This chapter defines the processes to be adopted following the completion of the Data Production processes defined in Chapter C, in order to install, test on site, and commission the data into service. It also defines the procedure to be adopted for the withdrawal of superseded data.
This document relates solely to the SSI-specific aspects of the defined processes. The general considerations of NR/L3/SIG/11303 and NR/L2/SIG/30014 continue to apply.
It is the responsibility of the Data Manager to confirm that all required activities in this Chapter (with the exception of testing) are carried out and a clear understanding shall be reached with the Tester as to the scope of the work.
Document History