scope:
The scope of Works and Services
The details of the scope of the Works and Services to be provided by the SP should be set out in Appendix A of the template which is effectively the works information or the specification. This section of the agreement still however requires a brief description or overview of the Works and Services to be inserted, which is cross referenced to Appendix A.
An example of how to complete Section 3 is:
The RP Requirements to be delivered by the SP are the management and construction of track and track side works at 20 separate locations across the SSL network including:
•Project management
•Delivery management
•Cost management3
•Detailed design
•Track works (including alteration and upgrading of existing)
•Points and crossing works (including alteration and upgrading of existing)
•Drainage works (including alteration and upgrading of existing)
Full details of the RP Requirements are provided in Appendix A
3 Generally cost management will always be undertaken by the SP