NR/L2/ELP/27715/MOD 05
Overhead Contact System Design Specification: Module 5 Engineering Deliverables - This standard should only be used for reference to ensure 'The Control of Risk' until the compliance date of its replacement standard is reached, upon which this standard will be withdrawn. The development of all new processes and procedures should be to the replacement standard
| Organization: | NR |
| Publication Date: | 3 March 2018 |
| Status: | active |
| Page Count: | 11 |
scope:
This module specifies the engineering deliverables for the design of OCS, including temporary works. It enhances the requirements in NR/L3/ELP/27406 and aligns design complexities with sufficient deliverables, focusing on ensuring key risks and design decisions are taken at an early stage.
It is applicable to:
• New electrification schemes;
• Modifications to existing OCS;
• Renewals of OCS;
• Temporary works impacting on the OCS.
This module is applicable to all OCS Designers.
Purpose
The purpose of this module is to specify the Network Rail requirements for production of Overhead Contact System (OCS) engineering deliverables to meet legislative requirements and to achieve safety, economy and performance.
This module provides a common strategy to demonstrate compliance and optimise the design of railway subsystems, but is not intended to reiterate legislation and governing standards.
Document History