NASA-LLIS-0062

Lessons Learned - LRU Platform Hoist and Tube Assembly; Platform Hoist Tube Assembly "UP" Limit Switch Bypass

active, Most Current
Organization: NASA
Publication Date: 5 March 1992
Status: active
Page Count: 2
scope:

Description of Driving Event:

Three sections of a telescoping tube assembly at Pad B rotating service structure (RSS) fell while being extended to incorporate a planned modification (MOD). The MOD intended to eliminate binding that had been experienced during testing and verification. The falling tubes impacted and severely damaged the RSS and orbital maneuvering system pod covers. The contributing factor to this failure is that the fillet welds on tube "D" provided an outward ramp effect that caused excessive wear on the keepers and the eventual bowing of tube "C" which allowed less surface contact area between the welded stops and the keepers.

Document History

NASA-LLIS-0062
March 5, 1992
Lessons Learned - LRU Platform Hoist and Tube Assembly; Platform Hoist Tube Assembly "UP" Limit Switch Bypass
Description of Driving Event: Three sections of a telescoping tube assembly at Pad B rotating service structure (RSS) fell while being extended to incorporate a planned modification (MOD). The MOD...