UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

NASA-LLIS-0528

Lessons Learned – Improperly Conceived Acceptance Tests and Original Specifications

active, Most Current
Organization: NASA
Publication Date: 5 October 1994
Status: active
Page Count: 2
scope:

Description of Driving Event:

In preparation for a test in the tow tank, Naval Underwater Systems Center personnel, who operate the facility under an MOU, sought the recommendations of IRD for the purchase of thirteen wet/wet pressure transducers with amplified outputs. The IRD recommended manufacturer was Druck and the appropriate specifications for transducers in their product line were provided to NUSC personnel. When the PR reached purchasing, the facility was informed that a GSA contract manufacturer would be the supplier. The GSA contract manufacturer was contacted by both NUSC and the instrument support section, IRD, since the needed items were not part of the GSA contract manufacturer's product line. The GSA contract manufacturer gave assurances that they could custom build the transducers to the required specifications. Twelve of the ordered thirteen transducers were delivered more than two months behind schedule and the thirteenth one-two weeks later. All the transducers passed acceptance tests and met or exceeded the original specifications. The first time the facility introduced a wet test medium (fresh water) into the transducers, the output of two transducers became very erratic and a third leaked water through welded seams in the transducer case. The two with erratic output were returned to the GSA contract manufacturer. The leaking transducer cannot be sent back without shutting down the in-progress test. Before the PR went out, ISS advised purchasing of the questionable quality of the GSA contract manufacturer's products, but according to purchasing, because of the GSA contract system, the GSA contract manufacturer had to be the supplier.

Document History

NASA-LLIS-0528
October 5, 1994
Lessons Learned – Improperly Conceived Acceptance Tests and Original Specifications
Description of Driving Event: In preparation for a test in the tow tank, Naval Underwater Systems Center personnel, who operate the facility under an MOU, sought the recommendations of IRD for the...
Advertisement