Lessons Learned – Facilities, Complete Contract Specs. Requirements
active, Most Current
| Organization: | NASA |
| Publication Date: | 23 August 1999 |
| Status: | active |
| Page Count: | 2 |
scope:
Description of Driving Event:
A water line coming into a building was being increased in size to accommodate a new building sprinkler system. The excavation was done, but the compaction that should have been done was not.
The specification of backfilling was not part of the contract documents.