NASA-LLIS-0495

Lessons Learned - Systems Engineering, System Safety and R&QA Program Integration, Operational Safety and Performance, Risk Management, and Facility Safety Inspections

active, Most Current
Organization: NASA
Publication Date: 28 February 1983
Status: active
Page Count: 2
scope:

Description of Driving Event:

December 9, 1982, the 80 x 120 foot wind tunnel at the Ames Research Center was undergoing commissioning/shakedown testing when Vane Set 5 collapsed destroying the vane set, the fan blades of all six drive motors, and damaging the tunnel itself.

Document History

NASA-LLIS-0495
February 28, 1983
Lessons Learned - Systems Engineering, System Safety and R&QA Program Integration, Operational Safety and Performance, Risk Management, and Facility Safety Inspections
Description of Driving Event: December 9, 1982, the 80 x 120 foot wind tunnel at the Ames Research Center was undergoing commissioning/shakedown testing when Vane Set 5 collapsed destroying the vane...