NASA-LLIS-0347

Lessons Learned - Impact of Industrial Mergers/Key Management Changes

active, Most Current
Organization: NASA
Publication Date: 21 October 1994
Status: active
Page Count: 2
scope:

Abstract:

When a contractor was absorbed by a second contractor early during the performance of the Mars Observer contract, the new contractor's management implemented methods that were not consistent with the original, agreed upon plans for integration and test. This created problems between JPL and the new contractor management.

Reconfirm the contract should major changes occur in the contractors organization, document critical technical and programmatic agreements, and revalidate agreements when changes in key personnel occur.

Document History

NASA-LLIS-0347
October 21, 1994
Lessons Learned - Impact of Industrial Mergers/Key Management Changes
Abstract: When a contractor was absorbed by a second contractor early during the performance of the Mars Observer contract, the new contractor's management implemented methods that were not...
Advertisement