NASA-LLIS-0278

Lessons Learned – Inadequate Time Allocated for Planning for DSN Support

active, Most Current
Organization: NASA
Publication Date: 12 July 1993
Status: active
Page Count: 2
scope:

Abstract:

Planning for the two-spacecraft Voyager mission did not consider the extra time needed to arrange for the allocation of Deep Space Network (DSN) coverage for the operation of both spacecraft. Lead times for project and institutional planning must be considered at the time the project mission operations plan is being developed.

Document History

NASA-LLIS-0278
July 12, 1993
Lessons Learned – Inadequate Time Allocated for Planning for DSN Support
Abstract: Planning for the two-spacecraft Voyager mission did not consider the extra time needed to arrange for the allocation of Deep Space Network (DSN) coverage for the operation of both...