NASA-LLIS-0749

Lessons Learned – Facilities, Mod/Rehab Projects, Construction Mtgs

active, Most Current
Organization: NASA
Publication Date: 23 August 1999
Status: active
Page Count: 2
scope:

Description of Driving Event:

Building Rehab projects are typically done on the second shift (4:00 p.m.-12:00 a.m.) and construction meetings are held every week to discuss the progress of the job. These meeting times and dates are left up to the participants to determine. The contract requires the meeting, but does not dictate a specific time.

The Contractor's job superintendent doesn't start work until 4:00 p.m. and when construction meetings start at 3:00 p.m. some valuable input from the field is missing. The Contractor's Project Manager is always in attendance, however the field representation is also required. If the meetings were moved until 4:00 p.m., many of the Government's representatives would not be in attendance due to their work schedule.

Document History

NASA-LLIS-0749
August 23, 1999
Lessons Learned – Facilities, Mod/Rehab Projects, Construction Mtgs
Description of Driving Event: Building Rehab projects are typically done on the second shift (4:00 p.m.-12:00 a.m.) and construction meetings are held every week to discuss the progress of the job....