NASA-LLIS-0115

Lessons Learned - Payload Bay Door (PBD) Opening/Closing Operations

active, Most Current
Organization: NASA
Publication Date: 27 July 1992
Status: active
Page Count: 2
scope:

Description of Driving Event:

During OMI V9023.F operations, the L/H payload bay door was noticed to have a slight upward bend in it due to excessive force placed on it through the L/H AFT PBD support jack. The aft half of the L/H PBD was raised eight to ten inches higher than the position of the PBD forward segment. An interference problem occurs when trying to insert/remove the "C" frame support hook from the support jack dowel. The interference problem requires the use of more than one technician to force the "C" frame support hook on and off the support jack dowel.

Document History

NASA-LLIS-0115
July 27, 1992
Lessons Learned - Payload Bay Door (PBD) Opening/Closing Operations
Description of Driving Event: During OMI V9023.F operations, the L/H payload bay door was noticed to have a slight upward bend in it due to excessive force placed on it through the L/H AFT PBD...