scope:
Practice:
Prior to shipment of hardware or software, conduct a pre-ship review at the completion of the fabrication or build and testing of the item to be shipped. This review is scheduled as part of the overall technical review program as defined in a project review plan. Pre-ship review is held at the supplier or NASA facility where the item was made and tested.
Document History
NASA-LLIS-0668
March 7, 2000
Lessons Learned – Pre-Ship Review
Practice: