NASA-LLIS-0047

Lessons Learned - Mercoid Pressure Switch; Inadvertent Water Deluge Activation

active, Most Current
Organization: NASA
Publication Date: 19 December 1991
Status: active
Page Count: 2
scope:

Description of Driving Event:

The primary cause of the mishap was an activation (closing) of the fire pump mercoid pressure switch which prematurely started the fire pump. This produced transient pressures that exceeded the 2:1 mechanical advantage of the deluge valves, forcing them open. The switch activation was caused by potable water system pressure fluctuations external to the local facility.

Document History

NASA-LLIS-0047
December 19, 1991
Lessons Learned - Mercoid Pressure Switch; Inadvertent Water Deluge Activation
Description of Driving Event: The primary cause of the mishap was an activation (closing) of the fire pump mercoid pressure switch which prematurely started the fire pump. This produced transient...