NASA-LLIS-0803

Lessons Learned – Identification, Control, and Management of Critical Items Lists

active, Most Current
Organization: NASA
Publication Date: 17 April 2000
Status: active
Page Count: 8
scope:

Practice:

Initiate the preparation of Critical Items Lists (CILs) early in programs to identify and potentially eliminate critical items before the design is frozen and as an input to hardware and software design, testing, and inspection planning activities. Utilize CILs during the operational portion of the life cycle to manage failures and ensure mission success.

Document History

NASA-LLIS-0803
April 17, 2000
Lessons Learned – Identification, Control, and Management of Critical Items Lists
Practice: Initiate the preparation of Critical Items Lists (CILs) early in programs to identify and potentially eliminate critical items before the design is frozen and as an input to hardware and...