NASA-LLIS-1411
Lessons Learned – Actively Manage Flight Project Risks During the Mission Operations Phase (2000)
| Organization: | NASA |
| Publication Date: | 1 January 2004 |
| Status: | active |
| Page Count: | 4 |
scope:
Abstract:
Cassini was one of the first major JPL missions to successfully conduct a risk management program during the Mission Operations and Data Analysis (MO&DA) phase. It was complicated by the distribution of the 500-person MOS Team across the U.S. and Europe, involving over 16 sub-teams, 9 time zones, and ITAR-mandated information exchange limitations. Define a formal risk management process early in MO&DA that will be tightly scoped to the operational phase of MO&DA. Also manage the human performance risks (fatigue, health, etc.) to mission ops. Select a flexible RM database tool.