Although the Deep Space 1 mission exceeded its overall technology demonstration objectives, certain important technologies under development never achieved flight readiness.
Develop a project implementation plan with preplanned alternatives that addresses technology readiness and risk mitigation. Cease development when technology readiness gates for critical technologies are not met and implement preplanned alternatives. Avoid a spacecraft architecture where one new technology relies on another in order to demonstrate them in-flight.