NASA-LLIS-1518
Lessons Learned - Early Involvement of Mission Ops is a Key Success Factor
active, Most Current
| Organization: | NASA |
| Publication Date: | 1 November 2004 |
| Status: | active |
| Page Count: | 3 |
scope:
Abstract:
Because the MER Flight Control Team (FCT) was fully formed only one month prior to MER launch, critical software engineering and operations management problems resulted. Staff FCT participation in project development at the beginning of Phase C and assure continued FCT involvement in project activities. Or at a minimum, select a few operations team members for early training.
Document History
NASA-LLIS-1518
November 1, 2004
Lessons Learned - Early Involvement of Mission Ops is a Key Success Factor
Abstract:
Because the MER Flight Control Team (FCT) was fully formed only one month prior to MER launch, critical software engineering and operations management problems resulted. Staff FCT...