NASA-LLIS-0928

Lessons Learned - KAO Aft Bulkhead Installation

active, Most Current
Organization: NASA
Publication Date: 6 November 1972
Status: active
Page Count: 2
scope:

Description of Driving Event:

The aft cavity bulkhead was built entirely outside the aircraft with no requirements to demonstrate the actual fit inside the aircraft. After manufacturing was complete, it was discovered that the aft bulkhead did not fit inside the aircraft. An investigation of this problem revealed that the dimensions on the drawings were incorrect. The aft bulkhead wall had to be removed and modified. This additional work cost the project a delay of about 3 weeks.

Document History

NASA-LLIS-0928
November 6, 1972
Lessons Learned - KAO Aft Bulkhead Installation
Description of Driving Event: The aft cavity bulkhead was built entirely outside the aircraft with no requirements to demonstrate the actual fit inside the aircraft. After manufacturing was...