LUL - OSN090

Route proving for the Northern line

active, Most Current
Organization: LUL
Publication Date: 7 June 2009
Status: active
Page Count: 7
scope:

General

Route proving has been used for some time on the Victoria Line to enable a train to pass a signal at danger or proceed after a SPAD incident, without the need to secure points. This minimises delay and reduces risk to staff who would otherwise have to go on the track to secure the points.

The process uses a proceed aspect of a signal reading over points to prove the points of a crossover are set in the correct position for a train on an adjacent line to proceed.

This procedure is now being introduced at approved locations on the Northern line. The procedure will work in the same way as on the Victoria Line, except that the train operator will need to stop and reset the tripcock after passing the signal at danger.