NASA-LLIS-0774

Lessons Learned - Electrical Isolation Verification (DC)

active, Most Current
Organization: NASA
Publication Date: 11 April 2000
Status: active
Page Count: 6
scope:

Practice:

Direct current (DC) electrical isolation verification tests are made as part of the EMC test of hardware prior to final spacecraft assembly. Flight acceptance isolation retest is required after any hardware rework of subsystems with electrical interfaces that utilize system wiring.

Document History

NASA-LLIS-0774
April 11, 2000
Lessons Learned - Electrical Isolation Verification (DC)
Practice: Direct current (DC) electrical isolation verification tests are made as part of the EMC test of hardware prior to final spacecraft assembly. Flight acceptance isolation retest is required...