NASA-LLIS-0482
Lessons Learned - Test Delays Due to Late Set-up of Instrument Ground Support Equipment (GSE)
| Organization: | NASA |
| Publication Date: | 7 November 1996 |
| Status: | active |
| Page Count: | 2 |
scope:
Description of Driving Event:
During laboratory system level integration and testing for a GSFC satellite at a contractor's facility, testing was delayed or reordered because of problems with the Instrument GSE. The Instrument teams arrived the same day that the testing was to start, and when the GSE was hooked up, there were problems. The ensuing troubleshooting process caused delays in the start of testing. In some instances, the test procedure was reordered to workaround the problem.