NASA-LLIS-0790

Lessons Learned – Problem/Failure Report Independent Review/Approval

active, Most Current
Organization: NASA
Publication Date: 17 April 2000
Status: active
Page Count: 3
scope:

Practice:

Problem/Failure (P/F) Reports are reviewed independently and approved by reliability engineering specialists to ensure objectivity and integrity in the closure process. This practice assures that the analysis realistically bounds the extent of the P/F, and the corrective action and its verification are successfully accomplished. The key elements are:

• Analysis must address the problem.

• Corrective action must address the analysis and the problem.

• Analysis must address the effect on other items.

• Corrective action must have been implemented.

• Item must have passed the gate that caused the P/F - the hardware/software must be successfully retested.

Document History

NASA-LLIS-0790
April 17, 2000
Lessons Learned – Problem/Failure Report Independent Review/Approval
Practice: Problem/Failure (P/F) Reports are reviewed independently and approved by reliability engineering specialists to ensure objectivity and integrity in the closure process. This practice...