NASA-LLIS-2456

Lessons Learned – Aquarius EGSE Shipping Mishap

active, Most Current
Organization: NASA
Publication Date: 16 February 2010
Status: active
Page Count: 3
scope:

A shipping container holding test equipment for the Aquarius project fell off the lift gate while it was being unloaded from a truck, and caused minor injuries to personnel. The root cause was inadequate planning and coordination of the transportation task. Use trained and certified personnel and equipment for critical equipment moves, perform a dry run of the operation, ensure that System Safety is informed and involved, and integrate contingency planning into transportation plans.

Document History

NASA-LLIS-2456
February 16, 2010
Lessons Learned – Aquarius EGSE Shipping Mishap
A shipping container holding test equipment for the Aquarius project fell off the lift gate while it was being unloaded from a truck, and caused minor injuries to personnel. The root cause was...