NR/L2/SIG/30009/E810

Signalling Principles Handbook: Reasonable Opportunity Assessment for Signalling Alterations

active, Most Current
Buy Now
Organization: NR
Publication Date: 7 December 2019
Status: active
Page Count: 18
scope:

This module provides methods and guidance in the identification of reasonable opportunities when works are proposed that affect or change the signalling assets or its records.

It applies to all works affecting signalling assets, including level crossings and S&C renewal. These include when:

a) equipment is renewed;

b) alterations are made to the layout;

c) layouts are re-signalled or relocked;

d) additional routes are provided;

e) lines are re-controlled.

This excludes individual component replacement under maintenance testing or functionally equivalent design.

Purpose

The purpose of this module is to critically examine project scope at a time in the design development whereby it is practicable to consider amending its limits. It challenges a preconceived belief that perpetuating existing arrangements is always tolerable. It encourages consideration of what may be reasonable to include, and highlights to the asset owner the residual risks that remain.

Following this module will reduce the post-project residual risk, be it performance, technical or safety related. It may give financial benefit in the short and long term depending on the merits identified for reasonable opportunity.

Document History

NR/L2/SIG/30009/E810
December 7, 2019
Signalling Principles Handbook: Reasonable Opportunity Assessment for Signalling Alterations
This module provides methods and guidance in the identification of reasonable opportunities when works are proposed that affect or change the signalling assets or its records. It applies to all...
Signalling Principles Handbook: Reasonable Opportunity Assessment for Signalling Alterations
All staff responsible for remitting or specifying works to the signalling system have an obligation to consider the ‘reasonable opportunity’ available for providing risk control measures as part of...
December 5, 2009
Signalling Principles Handbook – Interlocking Renewals
This specification applies to all signalling schemes and detailed design where the interlocking is renewed without alteration to the trackside equipment, layout, functionality or trackside apparatus...