PURPOSE
This John C. Stennis Space Center (SSC) standard (SSTD) establishes the requirements and procedures for completion and submittal of Certificate of Completion (COC), Form SSC-625, which is required for construction and renovation projects at SSC where any of the following conditions exist:
a. Facilities baseline documentation is affected as referenced in SSTD-8070-0001- CONFIG.
b. Facility value is increased by $5,000 or more.
c. There is new or replacement vendor data, which is required for all jobs including shop work orders.
d. Project involves changes to breaker panels.
APPLICABILITY
a. This SSTD applies to all SSC National Aeronautics and Space Administration (NASA) organizations, resident agencies, and contractors in accordance with the applicable requirements of SSTD-8070-0001-CONFI
b. This SSTD shall be maintained in accordance with SSTD-8070-0005-CONFI
c. Final authority for approval and interpretation of this SSTD resides with the NASA SSC Center Operations Directorate Project Management Division, and Operations and Maintenance Division.