scope:
Purpose and Scope
Line Procedure RT/CE/P/038 gives the requirements for managing the Track Geometry Recording Contracts and the actions required to deal with the detected track irregularities.
This Procedure summarises only those actions to be taken to deal with defects requiring Immediate or Urgent actions and the processes which the Infrastructure Contracts Manager must put in place in order to comply with RT/CE/P/038 in those respects.
It does not supplant RT/CE/P/038 in any respect, save for changing job titles for C-Change.