NR - RT/E/P/10175 ISSUE 12
Process for Management of TPWS Technical Instructions and Guidance Notes
| Organization: | NR |
| Publication Date: | 1 August 2003 |
| Status: | inactive |
| Page Count: | 16 |
scope:
This procedure only applies to Technical Instructions and Technical Guidance Notes produced by the TPWS National Project Team.
PURPOSE
This procedure details the process for managing the production of information that is specific to the TPWS project and needs to be published quickly to facilitate compliance with the RSR within the accelerated timescale.
The process is a truncated version of that required by the Network Rail Company Procedure, RT/LS/P/001 'Railtrack Line Policy on Standards'.Scope
Document History