NR/L2/TRK/3415 ISSUE 3
Refurbishment of Switches and Crossings (aka NR/L3/TRK/3415)
| Organization: | NR |
| Publication Date: | 4 March 2023 |
| Status: | active |
| Page Count: | 34 |
scope:
This standard applies to all S&C refurbishments carried out on Network Rail infrastructure.
It applies to all Network Rail and contracting staff that carry out the following activities for S&C refurbishment works:
• creating problem statements;
• scoping;
• specifying;
• delivery of the works;
• handback of works; and
• output review.
This standard does not supersede maintenance requirements or new construction requirements as part of a renewal or enhancement.
This standard does not supersede the requirement to comply with the Asset Management Plan (AMP) process.
NOTE: Maintenance requirements are covered by NR/L2/TRK/001. Design and construction of new assets is covered by NR/L2/TRK/2102. The AMP requirements are outlined in NR/L2/MTC/089.
Purpose
This document provides a process for the refurbishment of Switches and Crossings (S&C) assets.
The aims of this process are to:
a) improve scoping and planning of S&C refurbishment works to address S&C system risk;
b) promote optimal decision making to facilitate cost efficiencies and value for money;
c) provide additional guidance for the delivery of safe scoping and S&C refurbishment works, considering reasonable opportunity to replace legacy components with modern equivalents;
d) provide assurance that the S&C refurbishment works have addressed the track asset risk identified in the problem statement and the target asset life extension can be met; and
e) to provide alignment with Cost and Volume reporting structures.