scope:
The module covers:
a) Track, S&C and Off Track;
b) Traction Power/Power Distribution;
c) Telecoms;
d) Signalling;
e) Geotechnics, Structures, Tunnels and Buildings;
f) Plant;
g) Traction and Rolling Stock; and
h) Level Crossings.
Purpose
This module provides guidance on the steps required to move between route Category Levels and reintroduce a full operational service to lines following a period of reduced maintenance, service reduction and/or de-energisation.