scope:
This procedure shall apply:
- When identifying project tasks as closed
- When setting the Liability Period flag
- When changing project ownership
- When archiving to a new database instance
- When archiving to a XER
- When updating methodologies
Purpose
This document describes the process and procedures that shall be used to formally close a project within P3e.
This procedure implements within the Major Projects & Investment function and applies only to those projects that are delivered by Major Projects & Investment.