A pilot conducted on the CxP Extravehicular Activity (EVA) Project as part of the Agency's Earned Value Management Capability Project identified the need to emphasize the work authorization process to ensure traceability of scope, schedule, budget, and funding agreements.
Document History
NASA-LLIS-5676
March 22, 2012
Lessons Learned - Work Authorization Traceability