DSF/CLC/FprTS 50549-2
Requirements for the connection of a generating plant to a distribution system - Part 2: Connection to a MV distribution system
| Organization: | DS |
| Status: | inactive |
| Page Count: | 58 |
| ICS Code (Generators): | 29.160.20 |
scope:
The purpose of this Technical Specification is to provide technical guidance on the requirements for generating plants which can be operated in parallel with a distribution network. For practical reasons, this Technical Specification refers to the distribution system operator in case settings have to be defined and/or provided, even when these settings are to be defined and/or provided by another actor according to national and European legal framework. NOTE 1 This includes European network codes and their national implementation, as well as further national regulations. NOTE 2 Further national requirements especially for the connection to the distribution network and the operation of the generating plant can apply as long as they are not in conflict with this Technical Specification. The requirements of this Technical Specification apply to all generating plants, electrical machinery and electronic equipment, irrespective of the kind of primary energy source and irrespective of the presence of loads in the producer's network that meet all of the following conditions:
Document History