LUL - G1140
PMF, VAP and VAR Guidance for SQE Advisers
| Organization: | LUL |
| Status: | active |
| Page Count: | 8 |
scope:
Overview: VAP Guidance
As outlined in the previous section, all of LU‟s HSE requirements are embedded within PMF products. It therefore makes sense to align HSQE‟s verification activities with the PMF structure as much as possible. In the PMF world, all of HSQE‟s verification activities fall into one of two categories, both of which should be represented in each VAP:-
a) Quality checks on PMF products,
b) Product production & implementation checks.
VAPs, by their very nature, cannot be generic; the exact form
and content of Verification Activities needs to meet the
requirements and circumstances of each individual project. As such,
the VAP Guidance Spreadsheet associated with this document does not
provide a generic list of Verification Activities to be conducted
by all SQEAs across the Projects & Upgrades area but represents
an interactive tool intended to help SQEAs put together individual
VAPs suited to each of their projects/programmes.
Document History