LUL - G1252

Primavera Planning Database

active, Most Current
Organization: LUL
Publication Date: 1 August 2012
Status: active
Page Count: 67
scope:

The sum of the work content of a project

TfL Milestones

TfL Milestones are a key type of milestone used by TfL to monitor progress across the LU Enterprise Portfolio. TfL Milestones are typically a selection of LU‟s key PAMs and are agreed by the Executive Committee.

Work Breakdown Structure (WBS)

A deliverable orientated hierarchical arrangement of scope ranging from the highest level of management deliverable or asset groups down to detail task based activities. Used within MPD and Primavera

Unapproved Budget

This is defined as budget above and beyond the current financial year‟s TfL budget and/or the project authorised spend that the project manager predicts they will need to complete the project

Document History

G1252
August 1, 2012
Primavera Planning Database
The sum of the work content of a project TfL Milestones TfL Milestones are a key type of milestone used by TfL to monitor progress across the LU Enterprise Portfolio. TfL Milestones are typically a...
December 1, 2011
Primavera Planning Database
Introduction The London Underground (LU) Primavera Planning Database (PPD) User Guide is a supplement to the Master Projects Database (MPD) Desk Reference and supports the use of Primavera in...