scope:
PURPOSE
The purpose of this Marshall Procedural Requirement (MPR) is to define the methods and responsibilities for facility project planning at the Marshall Space Flight Center (MSFC).
APPLICABILITY
This procedure applies to facility planning activities performed at or under the direction of MSFC for projects exceeding local approval authority.
Document History
March 17, 2014
FACILITY PROJECT PLANNING PROCESS
PURPOSE
The purpose of this Marshall Procedural Requirement (MPR) is to define the methods and responsibilities for facility project planning in accordance with NPR 1400.1, NASA Directives and...
November 6, 2008
FACILITY PROJECT PLANNING PROCESS
PURPOSE
The purpose of this Marshall Procedural Requirement (MPR) is to define the methods and responsibilities for facility project planning by the Marshall Space Flight Center (MSFC)....
NASA MPR 8820.1 REV C
February 12, 2007
FACILITY PROJECT PLANNING PROCESS
PURPOSE
The purpose of this Marshall Procedural Requirement (MPR) is to define the methods and responsibilities for facility project planning at the Marshall Space Flight Center (MSFC)....
August 10, 2005
FACILITY PROJECT PLANNING PROCESS
PURPOSE
This procedure defines the methods and responsibilities for facility project planning at the Marshall Space Flight Center (MSFC).
APPLICABILITY
This procedure applies to facility planning...
September 27, 2004
FACILITY PROJECT PLANNING PROCESS
PURPOSE. This procedure defines the methods and responsibilities for facility project planning at the Marshall Space Flight Center (MSFC).
APPLICABILITY. This procedure applies to facility planning...