scope:
PURPOSE
This Marshall Procedural Requirements (MPR) defines the methods and responsibilities for design control of facility designs at the Marshall Space Flight Center (MSFC).
APPLICABILITY
This MPR applies to facility design activities performed at or under the direction of MSFC.
Document History
May 23, 2014
DESIGN CONTROL OF FACILITIES
PURPOSE
This Marshall Procedural Requirements (MPR) defines the methods and responsibilities for design control of facility designs at the Marshall Space Flight Center (MSFC) and MSFC’s Michoud...
October 20, 2008
DESIGN CONTROL OF FACILITIES
PURPOSE
This Marshall Procedural Requirements (MPR) defines the methods and responsibilities for design control of facility designs at the Marshall Space Flight Center (MSFC) and MSFC's Michoud...
NASA MPR 8823.1 REV C
August 22, 2005
DESIGN CONTROL OF FACILITIES
PURPOSE
This Marshall Procedural Requirements (MPR) defines the methods and responsibilities for design control of facility designs at the Marshall Space Flight Center (MSFC).
APPLICABILITY
This...