NR/L3/ELP/29987/MOD11 ISSUE 4
Working On or About 25 kV A.C. Electrified Lines: Working On Overhead Line Equipment
| Organization: | NR |
| Publication Date: | 5 September 2015 |
| Status: | inactive |
| Page Count: | 15 |
scope:
This module states the requirements to be met when working on the overhead line equipment on 25 kV a.c. electrified lines.
It is applicable to Network Rail personnel and to Network Rail's contractors.
To provide a consistent approach to working on or about 25 kV a.c. electrified lines, Train Operating Companies may, as best practice, apply this standard to infrastructure they control.
Purpose
This module will produce a consistent approach to working on the overhead line equipment of 25 kV a.c. electrified lines. Further requirements for working on or about the electrified lines are contained in the Rule Book Module AC (GE/RT8000/AC).
Document History