NR - RT/CE/P/038 ISSUE 3
TRACK GEOMETRY: MANAGEMENT OF RECORDING AND OF IMMEDIATE AND URGENT ACTIONS
| Organization: | NR |
| Publication Date: | 1 November 1996 |
| Status: | inactive |
| Page Count: | 11 |
scope:
This document applies to all Zonal Civil Engineers (ZCEs), Zonal Senior Contracts Managers (ZSCMs) and the Civil Engineer, Standards, Railtrack HQ.
PURPOSE
This document defines the procedure for ensuring that track geometry recording is conducted at the required frequencies using approved methods and that records of the track geometry are made during these monitoring runs with subsequent distribution, analysis and retention of the records. The monitoring process must also identify and report the location of sub-standard track. Where sub-standard track is identified this procedure includes those actions required to ensure the safety of the line until any necessary track repair is completed.