NR - RT/D/P/022 ISSUE 4
Management of the Monitoring of Contracts and Corrective Actions
| Organization: | NR |
| Publication Date: | 1 January 1998 |
| Status: | inactive |
| Page Count: | 19 |
scope:
This Procedure covers the checking of all activities carried out by the RTIA Contractor under the Infrastructure Maintenance Contract and recording and follow up of corrective actions.
The scope of this Procedure includes checks on Contractor's management systems, activities and end products.
Purpose
The purpose of this Procedure is to establish a system for the Management of Monitoring of Contracts and corrective actions follow up which shall ensure that the RTIA Contractor is satisfactorily maintaining Railtrack's Infrastructure. This Procedure outlines the roles and responsibilities of those parties involved in the management of the monitoring system and corrective actions.
Monitoring shall be performed on the basis of a statistically determined regime prioritised by the assessment of risk. The monitoring system shall check, as a minimum:
• Railtrack's Infrastructure assets are fit for purpose
• that Contractual and Technical compliance is being achieved
• the Contractors adherence to responsibilities set out in their Safety Case
• that Railtrack Plc's commercial interests are being safe-guarded
The minimum requirements to provide confidence to Railtrack that the Contractors Management Systems are effective and their End Products are acceptable are detailed in Procedure RT/D/P/015 "Generation of RTIA Contract Check Plans".
This Procedure amplifies the requirements as shown in the IDEF Element Process Map Box 5.2.2 "Measure Contractors Compliance" and Box No. 5.2.3 "Review Contractors Compliance".
Document History