NR/L2/OPS/031 ISSUE 5
Risk Assessment & Briefing of Timetable Change (aka NR/GN/OPS/031)
inactive
| Organization: | NR |
| Publication Date: | 26 August 2008 |
| Status: | inactive |
| Page Count: | 12 |
scope:
This standard covers the significant changes to service levels associated with the introduction of the new published timetables. It applies to both passenger and freight services.
Purpose
To set out the common process to identify, assess and control the risks associated with timetable change to as low as reasonably practicable (ALARP).
Document History
September 7, 2019
Assessing and Assuring the Impact of Operational Risks Relating to Changes to the Train Plan
This standard applies to:
a) all Network Rail Regions / Routes and Central Functions;
b) all aspects of the train plan that have the potential to impact the train service being operated safely and...
September 6, 2014
Risk Assessment and Briefing of Timetable Change
This standard describes the risk review and briefing of timetable change process and applies where any significant timetable change is being proposed.
The standard encompasses significant changes...
March 5, 2011
Risk Assessment & Briefing of Timetable Change
This standard encompasses significant changes associated with the introduction of the new agreed timetables and to incremental changes over time. It applies to both passenger (including ECS) and...
September 5, 2009
Risk Assessment and Briefing of Timetable Change (aka NR/GN/OPS/031)
This standard encompasses significant changes associated with the introduction of the new agreed timetables and to incremental changes over time. It applies to both passenger (including ECS) and...
December 1, 2008
Risk Assessment and briefing of Timetable Change (aka NR/GN/OPS/031)
This standard compasses significant changes associated with the introduction of the new agreed timetables and to incremental changes over time. It applies to both passenger and freight services....
NR/L2/OPS/031 ISSUE 5
August 26, 2008
Risk Assessment & Briefing of Timetable Change (aka NR/GN/OPS/031)
This standard covers the significant changes to service levels associated with the introduction of the new published timetables. It applies to both passenger and freight services.
Purpose
To set...
June 1, 2006
Risk Assessment & Briefing of Timetable Change (aka NR/GN/OPS/031)
This procedure covers the significant changes to service levels associated with the introduction of the new published timetables. It applies to both passenger and freight services.
Purpose
To set...
June 1, 2005
Risk Assessment & Briefing of Timetable Change
This procedure covers the significant changes to service levels associated with the introduction of the new published timetables. It applies to both passenger and freight services.
Purpose
To set...
April 1, 2004
Risk Assessment & Briefing of Timetable Change
This procedure covers the significant changes to service levels associated with the introduction of the new published timetables. It applies to both passenger and freight services.
Purpose
To set...
October 1, 2000
Risk Assessment & Briefing of Timetable Change
This Procedure covers the significant changes to service levels associated with the introduction of the summer and winter timetables. It applies to both passenger and freight services.
Purpose
This...