NR - RT/E/S/10662 ISSUE 1
Process for the Introduction of New or Revised Maintenance Regimes for Signalling Assets
| Organization: | NR |
| Publication Date: | 1 December 2000 |
| Status: | inactive |
| Page Count: | 30 |
scope:
This specification applies to all new and existing signalling assets on Railtrack controlled infrastructure.
This specification details the additional requirements (over and above those for the ongoing management of maintenance) associated with introducing new or revised maintenance regimes. It does not detail the requirements for the normal maintenance management system.
PURPOSE
This specification defines the minimum requirements for the introduction of new or revised maintenance regimes for signalling assets.
Document History