NR/SP/TRK/001 ISSUE 1
Inspection & Maintenance of Permanent Way
| Organization: | NR |
| Publication Date: | 1 August 2005 |
| Status: | inactive |
| Page Count: | 110 |
scope:
This specification applies to all inspection and maintenance of the permanent way. It sets out:
• mandatory frequencies for routine visual, ultrasonic and geometry recording inspections;
• procedures for carrying out the above inspections;
• details of those track defects which, if found, require immediate blocking of the line to traffic or imposition of an emergency speed restriction;
• methods for detailed inspection of certain major track components.
• maintenance of the permanent way including lineside items.
Additional requirements specific to continuous welded rail (CWR) are set out in RT/CE/S/011 Continuous welded rail (CWR) track.
Unless otherwise stated, the specification applies to all running lines and sidings open to traffic. For the particular requirements at leased depots see RT/CE/S/037 Requirements for maintenance of trackwork in depots by Depot Facility Operators.
The specification applies to permanent way which is undergoing renewal, or is in a temporary condition in connection with underbridge or other works, as well as to permanent way which is in normal maintenance.
Purpose
This is a system specification that gives the minimum requirements for the inspection and maintenance of Network Rail's permanent way.
Document History