scope:
This Practice describes the requirements for furnishing and installing ACIP piles. Probe piles and pile load tests are included and shall be executed in accordance with this specification when required.
Purpose
This Practice provides the constructor with requirements for the installation of augered cast-in-place (ACIP) piles.
Document History
April 1, 2019
Augered Cast-in-Place Piles Installation Specification
This Practice describes requirements for furnishing and installing augered cast-in-place (ACIP) piles also called continuous flight auger (CFA) piles. Test piles, pile load tests and pile integrity...
April 1, 2019
Augered Cast-in-Place Piles Installation Specification
This Practice describes requirements for furnishing and installing augered cast-in-place (ACIP) piles also called continuous flight auger (CFA) piles. Test piles, pile load tests and pile integrity...
PIP STS02465
February 1, 2012
Augered Cast-in-Place Piles Installation Specification
This Practice describes the requirements for furnishing and installing ACIP piles. Probe piles and pile load tests are included and shall be executed in accordance with this specification when...
March 1, 2005
Augered Cast-in-Place Pile Installation Specification
This Practice describes the requirements for furnishing and installing augered cast-in-place piles. Probe piles and pile load tests are included if within the contact scope of work.